Scope of work
75%
Concrete works
30%
Block works
0%
Metal Works
0%
Facade Works
0%
Finishing Works
3%
MEP Works
6%
Thermal & moisture Works
Latest Update: 2025-11-04
Project Details:
Offices Building Riyadh, spanning 42,000 square meters, is a groundbreaking project slated for completion within 14 months. The tower stands out with high-quality finishes and advanced electrical and mechanical systems designed to deliver an exceptional experience.
Scope of work:
Concrete works
Block works
Metal works
Facade works
Thermal and moisture works
Finishing works
MEP works
Location
Riyadh , King Abdullah Road
Industry
Construction
Area
42000
Timing
Start Date 15 July 2025 Contractual End Date 15 January 2026
Status
Under Construction
Client

Commercial | Commercial